[¿À¸¸] ¸¶¶óÇÈ, µÎÄñ ¼ö·Â ¹ßÀü ÇÁ·ÎÁ§Æ® ÀÔÂû ¸¶°¨ ¿¬Àå
¿À¸¸ÀÇ ¸¶¶óÇÈ(Marafiq)Àº µÎÄñ(Duqm) ¼ö·Â ¹ßÀü ÇÁ·ÎÁ§Æ®¿¡ ´ëÇÑ ÀÔÂû ¸¶°¨ ±âÇÑÀ» 8¿ù 1ÀÏ¿¡¼ 9¿ù 15ÀϱîÁö·Î ¿¬ÀåÇß´Ù.
ÃÖ´ë 8°³ÀÇ »çÀü ÀÚ°ÝÀ» °®Ãá ¾÷ü°¡ ´ëÇü °¡½ºÈ·Â¹ßÀü¼Ò ¹× ´ã¼öÈ ¼³ºñ¿¡ ´ëÇÑ ¼³°è¡¤½Ã°ø¡¤Á¶´Þ(EPC) °è¾à¿¡ ÀÔÂû¿¡ Âü¿©ÇÒ °ÍÀ¸·Î ¿¹»óµÈ´Ù. °è¾à ¼öÁÖ´Â ¾à 2018³â 1ºÐ±â°¡ µÉ °ÍÀ¸·Î ¿¹»óµÈ´Ù.
ÀÌ ÇÁ·ÎÁ§Æ®´Â 183¸Þ°¡¿ÍÆ®(§Ó)ÀÇ ¹ßÀü¼Ò¿Í ÇÏ·ç 4¸¸3õ§©/ÀÏÀÇ ´ã¼öÈ ¼³ºñ¿ë·®À¸·Î ±¸¼ºµÇ¸ç, ÁÖ·Î µÎÄñ »ê¾÷´ÜÁöÀÇ »õ·Î¿î Á¤À¯¡¤¼®À¯ÈÇдÜÁö¿¡ °ø±ÞµÉ ¿¹Á¤ÀÌ´Ù.
ÇÁ·ÎÁ§Æ®´Â Ÿī¹° ÅõÀÚ È¸»ç(Takamul Investment Company(65%))ÀÇ ÇÕÀÛ ÅõÀÚ»çÀÎ ¸¶¶óÇÈ(Marafiq)°ú ¼ÀÄß À¯Æ¿¸®Æ¼(Sembcorp Utilities(35%))°¡ ÁøÇàÇÏ°í ÀÖ´Ù.
[¿ø¹®º¸±â]
Oman's Marafiq extends bidding deadline for Duqm power and water project Omani utility Marafiq has extended the bidding deadline for Duqm power and water project from 1 August to 15 September 2017, reports Times of Oman.
Up to eight pre-qualified companies are expected to bid for the engineer, procure and construct (EPC) contract for a large gas-fired power plant and desalination facility. The contract award is anticipated in Q1 2018.
The project comprises a 183 megawatt (MW) power plant and 9.5 million imperial gallons a day (43,000 m3/d) of desalinated water capacity, and primarily will serve a new refinery and petrochemical complex in Duqm industrial zone.
It is being developed by Marafiq, a joint venture of Takamul Investment Company (65 per cent), and Sembcorp Utilities (35 percent), which serves the Special Economic Zone Authority of Duqm (SEZAD).
[Ãâó = Water. Desalination+Reuse / 2017³â 8¿ù 2ÀÏ]
|